How Many Yards of Concrete for a 12x20 Slab? (2026 Cost & Rebar)

Direct Answer: A 12'×20' (240 sq ft) slab requires 3.26 cubic yards at 4" thick (2.96 raw + 10% waste) or 4.89 cubic yards at 6" thick for a shop or vehicle lift. Add +3.04 yd³ for a 12"×18" monolithic perimeter footing.

Customize Your 12' × 20' Pour

240 Sq Ft
Slab Concrete Thickness

4" = residential/patio • 5"–6" = shop bays, RV storage & 2-post car lifts.

Exact Ready-Mix Order for 12' × 20' (4" Thick)1 Ready-Mix Truck (9.5 yd³ each)
6.3 Cubic Yards(5.7 raw + 10% waste)
Concrete Material
$1,071
@ $170/yd³
Turnkey Poured Est.
$3k–$4k
Labor, rebar & finish
#4 Rebar (16" OC)
22 Sticks
20-ft bars + 12% lap
4" Gravel Base
5 Tons
#57 crushed stone
Pour Breakdown: Flat 4" slab = 2.96 yd³ + 64 LF monolithic perimeter footing = 2.77 yd³. Mixing by hand would require 284 bags of 80-lb concrete mix—always order ready-mix transit trucks for a 12x20 structural slab.
12x20 Concrete Slab Thickness, Monolithic Footing & 2026 Cost Matrix
Slab ThicknessFlat Order (w/ 10% Waste)With 12"×18" Monolithic EdgeReady-Mix TrucksBest Application
4 Inches (3,500 PSI)3.26 yd³6.3 yd³1 truck(s)Residential living area, patio, light passenger cars
5 Inches (4,000 PSI)4.07 yd³7.1 yd³1 truck(s)Full-size 3/4-ton trucks, 2-post car lift (4.5"+ min)
6 Inches (4,000 PSI)4.89 yd³7.9 yd³1 truck(s)RV storage bays, tractors, heavy mechanic workshops
8 Inches (4,500 PSI)6.52 yd³9.6 yd³1 truck(s)Commercial fleet semi-trucks & heavy machinery

Frequently Asked Questions — 12x20 Concrete Slabs

How many cubic yards of concrete do I need for a 12x20 slab?

A 12' × 20' (240 sq ft) slab at 4 inches thick needs 2.96 raw cubic yards, or 3.26 cubic yards with a standard 10% waste buffer (1 ready-mix truck). At 6 inches thick for a shop or vehicle lift, order 4.89 cubic yards.

How much does a 12x20 concrete slab cost in 2026?

Ready-mix concrete delivery alone for a 4-inch 12x20 slab costs roughly $505 to $603 ($155–$185/yd³). A full turnkey contractor-poured 4-inch slab with gravel base, vapor barrier, #4 rebar (22 sticks), forming, and finishing averages $1,656 to $2,496.

How much extra concrete does a monolithic thickened edge add to a 12x20 slab?

A standard 12"-wide × 18"-deep monolithic perimeter footing around the 64 linear feet of a 12x20 slab adds approximately 3.04 cubic yards (including 10% over-excavation buffer).